November 2023 Construction Update

November 2023 construction updates:

  • The new entrance between the auxiliary gym and the main building is complete, as are the weight room and the gym and locker room upgrades.
  • The library has temporarily relocated to C House, which is available for study time and checking out materials. 
  • A temporary commons is under construction and will be available in January 2024. The existing commons will be closed off on December 20. 
  • Building A and the old administrative area will be demolished in mid-to-late November. Construction of the commons, new kitchen, and classroom building will begin after demolition.
  • Parking: Throughout the school year, students will park in the temporary lot available off Hoh Street. The west parking lot near the portables and the east parking lot near the tennis courts remain available for staff and visitors. All staff, students, and visitors must follow signage and park only in designated areas. 
  • For after-school activities, students and staff can access the theater and gym near the student store. Please note that beginning in January 2024, theater performances and other events will temporarily be scheduled at other locations due to construction.